[ad_1]
The National Nuclear Security Administration in a decision announced Wednesday stated that planning and construction could cost upwards of USD 4 billion initially. The agency doesn’t articulate what exactly that money would be spent on nor does it include the cost of other preparations that would be needed for Los Alamos National Laboratory to begin producing 30 plutonium cores per year.
The push to resume production of the nuclear triggers has spanned multiple presidential administrations, with supporters arguing that the US needs to ensure the stability and reliance of its arsenal given growing global security concerns. The nuclear agency also has said most of the cores in the stockpile date back to the 1970s and 1980s.
Democratic members of New Mexico’s congressional delegation have supported production at Los Alamos given the billions of dollars in federal funding and thousands of jobs that are at stake. But watchdog groups have been sounding alarms over the potential for more security and safety lapses at the northern New Mexico lab and the potential for environmental contamination.
Another concern is the nuclear waste that would be generated by the work.
Watchdog groups say the cost estimate outlined by the agency in its decision is roughly double the projections made just last year.
Greg Mello with the Los Alamos Study Group said the ballooning budget and uncertainty over whether the lab can meet the federal government’s mandated production schedule “throw further doubt on the wisdom of proceeding with industrial pit production” at Los Alamos.
“LANL’s facilities are simply too old and inherently unsafe, its location too impractical,” he said. “Even with a much smaller stockpile, LANL could not undertake this mission successfully.”
Some groups have threatened to sue the US Energy Department and the National Nuclear Security Administration, saying a more comprehensive review should have been done on the plans to produce plutonium cores Los Alamos and at the Savannah River Site in South Carolina. They argue that nearby communities already have been saddled with legacy contamination from previous defense work.
Jay Coghlan of Nuclear Watch New Mexico called the federal government’s plans “unnecessary and provocative,” saying more production will result in more waste and help to fuel a new arms race.
The nuclear agency in a statement said it expects to set cost and schedule baselines in 2023 as part of the ongoing process. It also plans to continue reviewing the project “to improve the fidelity” of price and timeline estimates.
Lab Director Thom Mason is scheduled Thursday evening to host a community meeting to talk about the lab’s work, which also includes projects related to space exploration, the coronavirus pandemic, water supplies in the arid West and wildfires.
[ad_2]
Source link